Project Snapshot

  • Name of Project: 220 kV and 132 kV Grid Substation and associated transmission lines and associated scheme/works under RAJ/PPP-8
  • Project Location: Rajasthan
  • Regulator – Rajasthan Electricity Regulatory Commission
  • Circuit Length: 115 Ckms
  • Transformation Capacity: 310 MVA
  • SCOD: February 2019
  • Actual COD: February 2019
  • Concession / TSA Term: 35 Years
  • Project Mode: Tariff Based Competitive Bidding (TBCB)
  • Project Type: Intra State
  • Project Rating: BBB+ (CARE)
  • Beneficiary State / Off-taker: Rajasthan
  • Business Model: Build Own Operate Maintain

Project Highlights

  • Project completion before scheduled timeline
  • Proven historical operating performance – achieved availability higher than target availability
  • Strong O&M team with maintenance plan ensuring periodic maintenance
  • Fixed tariff – all tariff through non escalable component

About the Project

HPTSL was incorporated on May 10, 2013. Hadoti Power Transmission Ltd. was awarded to ATL (Adani Transmission Ltd.) by Rajasthan Rajya Vidyut Prasaran Nigam Ltd. on Mar 31, 2017 for 35 year period on BOOM basis. HPTSL entered into a Transmission Service Agreement with Long Term Transmission Customer on Aug 11, 2017.

The transmission system established under HPTSL meets the power demand in the Rajasthan state. HPTSL operates five EHV overhead transmission lines with total circuit length of approximately 115 Ckms and five nos. Grid substation of 310 MVA capacity in the state of Rajasthan. The project construction started in November 2017 and was fully commissioned in February 2019.

Read more

Project Details

Transmission line/Substation Location Route Length (Ckms) / Transformation Capacity (MVA) Commission Date
LILO 220kV S/C Kota-Badod & Kota- Modak Line at Ranpur, LILO of 132 kV S/C Kota - Mandana Town line, LILO of 132 kV S/C Mahaveer Nagar Deoli Manjhi line & 220kV GSS Ranpur, Kota Dist. Rajasthan 30 Ckms, 210 MVA 20-Feb-2019
132kV S/C Malpura –Peeplu Line & 132kV GSS Peeplu, Tonk Dist. Rajasthan 40 Ckms, 25 MVA 13-Jan-2019
LILO of 132 kV S/C Seemalwara - Sagwara line & 132kV GSS Chitri, Dungarpur Dist. Rajasthan 4 Ckms, 25 MVA 30-Apr-2018
132 kV GSS Salumbar S/C line associated with 132 kV GSS Bambora & )132kV GSS Bambora, Udaipur Dist. Rajasthan 25 Ckms, 25 MVA 06-Jan-2019
LILO of 132 kV S/C Nadbai – Weir line associated with 132 kV GSS Khatoti & )132kV GSS Khatoti, Bharatpur Dist. Rajasthan 16 Ckms, 25 MVA 05-May-2018

Hi-Tech Infrastructure

Project Availability